CMB Carpi Logo Retina
  • Home
  • Company
    • What We Do
    • Values
    • History
    • Governance
    • Results
    • Commitment
    • Certifications
    • Becoming Suppliers
  • Media
    • News
    • Video
    • House Organ
    • Press Release
    • Press Kit
  • Work with us
    • Spontaneous Application
    • Internship
  • Contacts
    • Contacts
    • Contacts Milan Headquarter
    • Contacts Rome Headquarter
  • Projects
  • Facility Management
  • People
  • Safety
  • Innovation
    • Building Information Modeling
    • Success Project
    • Leed Certification
  • IT
  • EN
Menu
  • Home
  • Company
    • What We Do
    • Values
    • History
    • Governance
    • Results
    • Commitment
    • Certifications
    • Becoming Suppliers
  • Media
    • News
    • Video
    • House Organ
    • Press Release
    • Press Kit
  • Work with us
    • Spontaneous Application
    • Internship
  • Contacts
    • Contacts
    • Contacts Milan Headquarter
    • Contacts Rome Headquarter
  • Projects
  • Facility Management
  • People
  • Safety
  • Innovation
    • Building Information Modeling
    • Success Project
    • Leed Certification
  • IT
  • EN
  • it
  • en
03/12/2020

Salerno-Reggio Calabria A3 Motorway

Cosenza
ITALY

Between north and south, built on solid pillars of legality and in record time

The stretch of motorway between Salerno and Reggio Calabria is the highest in Europe: in several areas it stands over one thousand metres high.

It is a concentration of every possible type of infrastructure including the adaptation of viaducts with significant spans and heights. CMB has signed a so-called ‘Legality protocol’ in an aim to prevent, control and combat any attempts of mafia infiltration. It has also honoured its commitment to build a macro stretch of 20.5 km in just 30 months, over a year ahead of schedule.

EXPLOSION TIME
To remove the old steel structure, explosive was set up in several points. The bolster and the bridge were then built on the old pillars.

cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-02
cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-03
cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-04
cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-05
cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-06
cmb-salerno-reggio-calabria-infrastrutture-viadotto-italia-gall-07
20,5
km, length of lot 3.2
11
viaducts
6
tunnels
Technical Description

The macro lot 3.2 of the Salerno – Reggio Calabria motorway, now renamed the motorway of the Mediterranean, covers a distance of 20.5 Km, with 11 viaducts totalling 7,342 m and 6 tunnels, including both natural and artificial tunnels totalling 11,459 m. The construction site was located in the National Park of Pollino, an area with a turbulent mountainous landscape with peaks exceeding 2,200 m a.s.l., alternated with stunningly beautiful deep valleys.

The upgraded 20.5 Km stretch of motorway meanders its way through this complex landscape. The construction focused on the legislative adaptation of the route: the bend radius was increased to enable greater speed; the carriageways were widened, emergency lanes were built in each direction and a traffic divider was erected. Finally, all other fittings and safety structures were put in place. The most emblematic and adventurous part of the entire project is the ‘Italia viaduct’ over the Lao river, which has for many years been the highest in Europe. It is 1,161 m in length, a central span of 175 m and stands 261 m over the valley below. The tallest pillars reach a height of 130 m.

A3, the nerve centre for the south

The route of the Salerno-Reggio Calabria motorway built by CMB is a nerve centre for the entire motorway network. The work involved the construction of a new route between the junction of Laino Borgo and that of Campotenese (province of Cosenza), which consists of 60% of new road, 6 tunnels and 11 viaducts. The flagship of the entire construction is the ‘Italia Viaduct’: with a length of over 1,120 metres and a height of 260 above the valley below, it is the second highest viaduct in Europe.

The A3 motorway at a glance

Take a look inside the construction of the Europe’s highest motorway.

> Guarda l’infografica

Value of the works
424.512.090,93 euro
Client
ANAS Spa
Role in the project
Project leader
Completion times
June 2014 – December 2016
see also

Tramway Line 3 Florence

2018

Road access to the Expo 2015 area Milan

2015

Variante di Valico - A1 Motorway Lagaro (BO)

2015
Share this page
Share this page
Back to top
CMB Carpi Logo

P.IVA 00154410369
Registro delle Società di Modena
n. 00154410369 – C.C.I.A.A. 2698
Albo Cooperative n. A100255

©2018 CMB
Cooperativa Muratori e Braccianti di Carpi
Tutti i diritti riservati / All rights reserved

PROJECTS

FACILITY MANAGEMENT

PEOPLE

SAFETY

INNOVATION

COMPANY
What we do
Values
Enterprise’s History
Governance
Results
Commitment
Certifications
Becoming Supplier

LAVORA CON NOI

MEDIA
News
Video
House Organ
Press Release
Press Kit

SOCIAL NETWORK
Linkedin
Youtube

CONTACTS
Sede Centrale
via C. Marx 101 Carpi (MO) – ITALY
Ph +39 059 6322111
Fax +39 059 691079

Privacy Policy
Cookie Policy
Credits